No room for uncertainty: final date for payment must be tied to the due date

In Deerns UK Limited v VDC LHR11 Limited [2026] EWHC 1509 (TCC), a consultancy agreement that allowed for the final date for payment to be postponed if the consultant issued an invoice later than the application for payment was found